Work to restore green space to Deptford is progressing well over recent weeks after the completion of Thames Tideway work.

For some years the entire area near St Paul’s church was a large construction compound but is now returning to its former use – albeit landscaped in a different fashion.

Thames Tideway site render

Note the four ventilation shafts visible above. These can also just about be made out in the main image.

Changes to Deptford Church Street are also underway running beside the park. Construction had reduced road width from two lanes to one in each direction which will mostly be retained.

Deptford green space. Deptford Church Street changes on right

New cycle lanes are being installed alongside additional crossings.

A look at those changes was recently covered on this site.

Thames Tideway tunnel

The newly constructed tunnel cost £5 billion and was fully connected in February.

For a view of what’s underground in this part of Deptford take a glance below.

Diverting sewer to new tunnel

Note how an existing sewer is intercepted removing waste water during storms before its directed to Greenwich pumping station.

Work around Greenwich pumping station saw path width restrictions around the Ha’penny Hatch across the creek.

Landscaping work is also underway on the Greenwich side though of a much more limited variety than in Deptford.

Much of the Greenwich construction site beside Norman Road looks set to return to industrial usage, though work continues on housing development Saxon Wharf just to the north.

Quite the change then around Deptford which will continue in future with planned pedestrianisation of Deptford High Street as well as a 31-floor tower on the nearby Lewisham College site.

Two other projects apparently stuck in long-term limbo are Sun Wharf beside the creek alongside Laban Centre expansion alongside a new residential tower.

 

Independent sites can only continue with the support of readers.

You can support me via Paypal here

There's the Ko-fi option to buy me a coffee

Many thanks

You can also support the site by adding the Murky Depths as a trusted source in Google here

There's also a Facebook page for the site here

2 thoughts on “Deptford park taking shape after Thames Tideway completion”

  • It’s a disgrace they’ve left the road in that state after years of work ms destroyed the surface. It’s impossible to cycle or drive in it

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.