Greenwich cycle lane delays: A 14-week hold-up despite near completion for months

With all the fanfare this week of work beginning on another stretch of Cycle Highway 4 in Deptford, the wait to open a stretch from Deptford to Greenwich that’s been nearly complete for months continues.

Creek Road bridge

A delay was reported this week on 853, and today Greenwich West councillor Aidan Smith has stated it will be another 14 weeks until the Creek Road stretch opens.

And as stated, costing and agreement for funding are still ongoing.

Three months ago I went and looked at the near-completed stretch for a post.

Work was almost complete in May

 

Apart from a couple of areas it seemed good to go. Assuming costing is agreed, we are looking at seven months on from that visit.

The issue is focused on Creek Road’s rising bridge and who should fund repair work alongside the cycle lane, and if certain pots of money can cover certain areas of spending.

This has all the makings of another blame game between TfL and Greenwich Council and it’s far from the first time.

Not on the same page

Even on this stretch of cycle lane, during consultation Greenwich asked to retain guardrailing which went against TfL policy – as evidence and studies have shown in many areas it proves more dangerous. Lewisham asked for a feeder cycle lane.

TfL ignored Greenwich in the consultation report and agreed to Lewisham’s request.

Work at the major junction on Creek Road near Waitrose also typifies the problem. Greenwich Council spent large sums installing the junction using extremely dated design philosophy around 2014. Anti-pedestrian features and clutter which went against TfL streed design guidance abounded. It’s now all being replaced.

Replaced after a few years

The notorious roundabout at the Angerstein roundabout has finally seen changes after years of TfL and Greenwich “discussion”.

Still gloomy. Painting, murals, lighting? Anything?

Greenwich appear to have won the argument to retain extensive railings and actually installed yet more after work completed, and money went there instead while the area is still a gloomy, off-putting place despite the new cycle lane cut-through. It’s better, but far from what it could be with better lighting and street furniture to encourage usage.

TfL still manage to plough on with Silvertown Tunnel of course. While the bulk of funding is via private finance who will recoup through tolls, TfL are still spending up to £200 million.

Between Greenwich’s almost complete lack of understanding that attractive, open, appealing street design encourages walking and cycling, and TfL’s budget issues, it doesn’t bode too well.

 

 

 

------------------

Adverts are far from enough to cover site costs and my rent.

You can support me via Paypal here

Another option is via Patreon by clicking here

You can also buy me a beer/coffee at Ko-fi here

There's also a Facebook page for the site here

Many thanks

J Smith

I've lived in south east London most of my life growing up in Greenwich borough and working in the area for many years. The site has contributors on occasion and we cover many different topics. Living and working in the area offers an insight into what is happening locally.

4 thoughts on “Greenwich cycle lane delays: A 14-week hold-up despite near completion for months

  • A sorry state of affairs indeed John. One wonders how long China would take to construct a simple cycle lane along a lie of so stretch of already surfaced road. A week? Allow a couple more years over here, probably open same time as the dreaded new tunnel.

    Reply
  • auto correction- mile or so stretch

    Reply
  • And probably wouldn’t have messed up the traffic light phasing, and the now redundant “no left turn” coming out from Waitrose.

    Reply
  • Will have to be bulldozered anyway, when the current cupcakes from Greenwich council will go.

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.