Update given on Lewisham town centre £24m market and High Street project

Lewisham Council have given an update on work across the town centre now underway and set to bring a new market place, revamped library and High Street.

A report gives a number of dates when  work should be completed, with the High Street work expected to finish by September 2025.

Canopy and public realm changes on the way

Following on is the market canopy with a target date of March 2026 for construction and opening. Plans were approved in July 2024.

A budget of £1.6 million is allocated out of a total project spend of £24 million.

Proposed market canopy

Funding

£19 million of that funding was announced by the previous government as part of “levelling-up” funding, with £5 million match funding from Lewisham Council.

The report notes that a decision is expected from the borough’s Mayor & Cabinet on 18th Sept 2024 to “seek approvals for the procurement of the market canopy”.

Current High Street appearance

Bus diversions were introduced last month to enable High Street public realm work to commence, with the report stating buses will continue to divert via Molesworth Street until spring 2025.

The town’s clocktower is also to be renovated, and “tender documentation has been developed for the renovation works for the clock tower” which will be carried out alongside the market canopy.

Lewisham clocktower

Culture and Business Hub

This is the library revamp given a fancy name and is expected to complete by September 2026.

As covered in July this year, a rooftop bar has been scrapped.

Work is due to begin on site in 2025. The full report updating councillors can be read here.

 

 

Independent sites can only continue with the support of readers.

You can support me via Paypal here

There's the Ko-fi option to buy me a coffee

Many thanks

You can also support the site by adding the Murky Depths as a trusted source in Google here

There's also a Facebook page for the site here

3 thoughts on “Update given on Lewisham town centre £24m market and High Street project”

  • Charles Calthrop

    I notice an inordinate amount of seating for eating out: this would work very well if carefully marshalled (have a look at the excellent Five Continents food place in Stratford mall) so that it isn’t used as an extension of the shops nearby or for the hundreds of shoppers wanting somewhere to sit down. Still, a welcome idea, particularly if they address the appalling paving that runs the gamut from trip to cripple.

    Reply
  • The bus diversions are much better than the normal northbound route.

    Reply
  • anonymous201486

    @Chris L: I disagree. It’s a fair old walk, especially with shopping, from what was stop V (Lewisham Centre), through the Centre and down Molesworth Street to where TfL has determined the bus stops be placed.

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.